Wednesday, August 18, 2010

Welcome back!!!

Can you believe it? Summer's over and we are back to Channing Hall for our 5th year! We have some great projects coming up for our 5th year to celebrate our accomplishments. Speaking of which; how about the new addition and new field! The field is seeded, so now we just wait for mother nature to bring out the green!The playing field looks GIGANTIC!
The expansion is also 2 weeks ahead of schedule and should be completed by the first week of September. Hooray!The portables will be going away soon and we will be adding 9 new parking spaces there instead!

We're getting a great start to the 5th year already!

Let's keep it up!

Monday, August 2, 2010

Taking shape

Dust is flying, nails are shooting, men are hammering! The expansion is in full force!
All's a whirlwind of activity at Channing Hall working towards completing this as close as possible to school start.
The rooms are being wired. The windows are in.

Even the new field is progressing. The fence is down and the land is about leveled ready for the sprinkler system. Next will be the hydro-seed, fencing and then the patient wait for the seeds of all our planning and hard work to show.

Wednesday, July 14, 2010

Expansion update

The floor is in. The face is gone! GO! GO! GO!

Thursday, July 8, 2010

Construction update

Footers are in. Back-fill is in. Let's hope the construction accelerates significantly next week.

Keep tuned in.

Thursday, June 24, 2010

Work has started!

Here's a great sign! Digging of the foundation has begun. We expect it to ramp up significantly soon! Keep posted.

Monday, June 21, 2010

CHANNING HALL EXPANSION HEADQUARTERS

The CH expansion you have been hearing about finally officially started today. Tune in hear to follow the progress.
Here are the general floor plans for the expansion. We are excited to have all that extra room! the CTE room will even have sinks!!!The second level will have two big rooms plus a breakout room and lots more lockers. We will be adding just a bit over 4000 sf.

The expansion is funded by an American Recovery Act loan, Special ED loan and by a portion of the Annual Giving donations. THANK YOU DONORS for helping make this happen!

Wednesday, June 2, 2010

FUN RUN 2010! .......FUN!




Wow! What a nice day and what fun the kids had today! And this was all in the name of fitness and to help the school out. The kids ran thier hearts out then got to cool off with popsickles and a spraydown from Draper Fire. Thanks to all the hard working CHAPS parents for the hard work! THEY RAISED OVER $10000!!!! This money will all go back to the school to help with computer needs.


Heres some more fun pictures of the run.